BACKGROUND
HMP Glasgow is the new modern prison to replace the 143 year-old HMP Barlinnie site and has an additional 357 places within the overall prison estate taking capacity to a total of 1,344. The existing HMP Barlinnie was built in 1880 and is in critical need of replacement with the prison’s infrastructure deemed not fit for purpose by HM Inspectorate of Prisons in a recent report. HMP Glasgow will improve opportunities for successful rehabilitation whilst creating a safer working environment for staff.
The site itself once housed a gas works and will ensure a disused parcel of land is put to good use whilst ensuring economic benefit to Glasgow the use of local labour and businesses. Remedial work began on-site October 2023 and it was identified that significant piling work was required by Roger Bullivant over multiple phases of the site.
CHALLENGES
The team at Roger Bullivant Limited identified the logistical challenge of scheduling deliveries from its manufacturing depot in Swadlincote to site in a manner that would align with the project’s phased programme and meet key deadlines
Deliveries had to be made consistently on time to pre-determined schedules whilst also allowing scope to bring forward deadlines or delay them depending on progress or delays on-site. Deliveries were required to be spaced out to ensure site traffic was safely managed without impacting other contractors and trades who were working on site at the same time.
Eradicating any disruption due to transportation issues was a key factor in Roger Bullivant Limited securing the piling contract on this site and they required a proactive approach to ensure materials were available when needed.
SOLUTION
From the initial implementation of deliveries, we collaborated with the team at Roger Bullivant Limited to develop a delivery schedule showing timelines for each phase of HMP Glasgow and identified where demand may peak or be constricted by site conditions.
Weekly forecasts allowed us to coordinate vehicles to meet demands and daily reporting highlighted where further capacity was required.
Our drivers were all inducted at the HMP site which reduced turn around time on-site and ensured deliveries were made safely with all protocols and site rules followed to create a no problem solution.

PROJECT:
HMP Glasgow – HMP Barlinnie Replacement
SECTOR:
Construction
CLIENT:
Roger Bullivant Limited

WHAT WE ACHIEVED
100%
Success rate for meeting delivery schedules for each phase of HMP Glasgow
Over 55,000
Linear metres of piling material delivered
355
Deliveries made to site
“The successful delivery of our HMP Glasgow project was supported significantly by the exceptional service provided by the H&R Gray Haulage Limited team. Their excellent cooperation, flexibility, and unwavering commitment to meeting demanding programme requirements played a significant role in our execution of the project’s piling packages.
Despite the high volume of deliveries required, H&R consistently maintained a reliable service that ensured our works progressed safely, productively, and without disruption. Their ability to coordinate and implement just-in-time (same day or next day) deliveries was particularly valuable, minimising site congestion while ensuring materials were always available when needed. With over 55,000Lm of piling product installed on site over multiple phases, H&R successfully managed the delivery of over 350 loads to site, often with 10+ loads daily at peak.
Their professionalism, communication, and proactive approach made them a valued supply chain partner, and we look forward to continued co-operation on future projects.”
Owen McVerry, Contracts Manager
Roger Bullivant